The government will overhaul the power grid impact assessment system to speed the construction of AI data centres (AIDC). In AIDC zones, it will exempt non-technical assessments and introduce a priority-review system for large projects.

The Ministry of Science and ICT and the Ministry of Climate, Energy and Environment said on Thursday they will pursue reforms to tailor the power grid impact assessment system for AIDC.

In the enforcement decree of the AIDC special law, which was put up for legislative notice on Thursday, the government set the exemption threshold for power grid impact assessments for non-capital AIDC at contracted capacity of 50 megawatts or less. The government also considered that even if the exemption threshold is raised to 100 megawatts, most gigawatt-class large AIDC would not be included in the exemption. It also reflected industry views that preparing non-technical assessments takes considerable time. The science ministry and the climate ministry decided to pursue simplified and prioritised assessment procedures to support rapid construction of large AIDC.

The government will exempt non-technical assessments, which are part of the power grid impact assessment, for facilities in AIDC zones regardless of size. Technical assessments to confirm impacts on the power grid will still be carried out.

The climate ministry plans to revise regulations on operating the power grid impact assessment system. It will also strengthen links between AIDC zones and special distributed energy zones.

It will also set up a fast-track for large AIDC. AIDC that qualify as megaprojects promoted by the government, or that apply for bundled licensing under the AIDC special law, will be able to receive priority power grid impact assessments regardless of size.

The climate ministry plans to specify priority-review provisions in the power grid impact assessment manual it is currently preparing. It aims to reduce assessment wait times and bring forward the start of construction.

The government plans to apply the improved system in line with the AIDC special law taking effect on March 10 next year, after revising related public notices and preparing detailed manuals.

Ryu Je-myoung (류제명), second vice minister at the Ministry of Science and ICT, said the ministry worked closely with the climate ministry to prepare tailored improvements so AIDC can be built on time. He said he will work to ensure the improved power grid impact assessment system is established without disruption in line with the law taking effect.

Lee Ho-hyeon (이호현), second vice minister at the climate ministry, said he will swiftly complete revisions to public notices and detailed work manuals so the government can support rapid construction of AIDC, including megaprojects, while maintaining power grid stability.